product series
Executive Standard
IEC 60076-1-2011 |
Power Transformers-Part 1: General |
IEC 60076-2-2011 |
Power Transformers-Part 2: Temperature rise for liquid immersed transformers |
IEC 60076-3-2013 |
Power Transformers-Part 3: Insulation levels, dielectric tests and external clearances in air |
IEC 60076-4-2002 |
Power Transformers-Part 4: Guide to the lightning impulse and switching impulse testing-Power trans formers and reactors |
IEC 60076-10-2001 |
Power Transformers-Part 10: Determination of sound levels |
IEC 60296-2012 |
Fluids for electrotechnical applications - Unused Mineral insulating oils for transformers and switchgear |
IEC 60422-2013 paragraph 8 |
Mineral insulating oils in electrical equipment - Supervision and maintenance guidance |
IEC 60076-18-2012 |
Measurement of frequency response |
Shenda quality management:
- 100MVA/220KV power transformer --- short circuit test report from CESI Italy
- 120MVA/33KV EAF transformer; 50MVA/69KV Oil power transformer; 10MVA/33KV Dry type transformer ---Type test report from KEMA Netherlands
- 63MVA/110KV Power transformer ---short circuit Test report - Issued by CTQC China
- 12.5MVA/22KV Rectifier transformer--- routine test - Issued by V-check Korea
- ISO9001&ISO14001&OHSAS18001
- Power transformer & Furnace transformer & dry type transformer & Reactor ---CE
Factory documentation Model
During the design process, client will be permitted to come to factory to take a supervision and guidance, manufacture and acceptance test.
We provide engineering services like pre-commissioning / commissioning / install and operation consult support / technicians training on site.
We provide after-sales service.
We provide 12 months warranty of quality and performance
Company Introduction
Shenda ( In full: Shenda Electric Group Co.,Ltd.) is one of the leading manufacturers in the power transmission & distribution industry. Founded in 2000 and currently employs about 1,100 employees worldwide. Shenda operates four factories (three in China and one in the United States of America - R. E. Uptegraff Manufacturing Company, LLC of Pennsylvania, U.S.A.). Shenda also owns other ten subsidiaries throughout China. The annual gross sales is USD$250 million in 2015.
Shenda's annual total production capacity is about 18,000,000 KVA, Our main products include oil immersed power transformer(up to 250MVA/ 330kV) , dry type transformer(up to 20MVA/35kV), combined transformer substation, amorphous alloy transformer, rectifier transformer (100MVA/220kV )and especially furnace transformer(180MVA/220kV). Our products' performance measures up to the standards established by International Electric Committee (IEC).
shendaelectric.en.made-in-china.com
Test lab
Testing are conducted for every transformer before delivery.Tests are classified to be routine tests and type test.
A - Routine tests: According to IEC 60076 standard , the following tests must be carried out for all units of the transformers
- Measurement of winding resistance .
- Measurement of voltage ratio and check of phase displacement.
- Measurement of short circuit impedance and load losses.
-Measurement of no-load losses and current .
-Dielectric routine tests including the separate source AC voltage withstanding test and short duration induced over voltage withstanding test ( ACSD ) .
B - Type tests :
The following tests shall be carried out
- Temperature rise test
- Lightning impulse test
C - Special tests :
- Determination of noise level according to IEC 60551 .
- Oil leakage test
- Overload test at 150 % rated current for one hour after temperature rise test ( top oil temperature rise and winding temperature rise must be measured and recorded in the report test also hot spot temperature rise must be calculated and recorded on the report test ) .
- Short Circuit Dynamic stability Test (test report from independent and accredited laboratory for similar transformer will be accepted).
Client inspection
Packaging and transportation
Factory documentation
1 |
Technical parameters |
2 |
Outline drawing |
3 |
Lifting diagram |
4 |
Nameplate drawing |
5 |
Control box drawing |
6 |
Transportation diagram |
7 |
Transformer install manual |
8 |
Transformer operation / Maintenance instruction |
9 |
Principles parts / components ex-work certification and operation instruction |
10 |
Recommended spare part for 2-5 years operation |
11 |
Test reports (routine test / type test / special test) |
12 |
Etc… |
Engineering Services
During the design process, client will be permitted to come to factory to take a supervision and guidance, manufacture and acceptance test.
We provide engineering services like pre-commissioning / commissioning / install and operation consult support / technicians training on site.
We provide after-sales service.
We provide 12 months warranty of quality and performance